Challenge
The comms room at an aerospace testing facility experienced a power surge which took out all 3 air conditioning units. Within an hour the room was measuring over 75°c and the servers were all shutting down from overheating.Solution
A very simple Loxone system monitoring the air temperature and the surge protection device (newly fitted) with email alerts as an early warning of rising temperatures or surge depletion.(Unfortunately due to the nature of the work conducted by the client, limited information can be shared including images)
We are very pleased that the client went with this option and we're already looking at further things we can utilise the Loxone system for. The challenge of working on such a high security site adds another layer of problem solving which I personally really enjoy.
Lee MorrisDesign & Commissioning