Public charging park

Challenge

The company SUMIDA has set up a public charging park at the Erlau site with the following charging points:



- 4x 200 kW DC (Alpitronic Hypercharger)



- 6x 22 kW AC (Technagon P40 + P80)



- 7x 22 kW AC (Technagon P40)



A peak load management system is to be created for these charging points in order to avoid expensive peak loads.



In addition, possible fault messages at the charging stations are to be monitored.



In addition, the lighting of the charging park is to be controlled, the control cabinets and technical rooms are to be monitored for temperature and humidity, and the energy flows are to be visualized.

Solution

Peak load management with load manager.

Fault monitoring via Loxone app.

Visualization with energy flow monitor.

Monitoring with temperature and humidity sensors and corresponding alarms.

With Loxone it was possible to intelligently link the different charging point manufacturers. <br /><br /> This means that in the future the charging park can be operated in a cost-optimized manner and with the maximum possible performance.