Bogeart Logistics Warehouse

  • Country FR, Dunkerque
  • Build year 2024
  • Area 20 000 m² m²
  • LOXONE partner SAS SPE CONNECT
Bogeart Logistics Warehouse

Challenge

The Bogeart Group wanted to optimize the energy management of its industrial site, comprised of four 5,000 m² units, for a total surface area of 20,000 m², while ensuring the thermal comfort of the occupants.

The main technical challenges were:

- Implementing a high-performance, centralized building management system (BMS) enabling precise heating control.

- Ensuring hydraulic regulation in the boiler room through the creation and control of hydraulic valves.

- Supervising and controlling 32 air heaters (8 per unit) via two-way valves to optimize heat distribution.

- Guaranteeing reliable and representative ambient temperature measurements through the installation of two sensors per unit, with average temperature calculations to refine regulation.

- Integrating precise energy metering through the installation of heat meters on the hydraulic circuit.

- Carry out all work on an occupied site, without disrupting industrial activity.

Solution

We deployed a complete building management system (BMS) based on Loxone technology, enabling centralized, scalable, and high-performance monitoring of the heating system, including:

- Creation and control of hydraulic valves in the boiler room for precise heating management per unit.

- Individual control of the 32 air heaters via two-way valves, ensuring precise flow modulation and energy optimization.

- Installation of 8 ambient temperature sensors (2 per unit) with integrated averaging logic within the BMS for more stable and consistent regulation.

- Integration of heat meters on the hydraulic circuit to allow for detailed energy monitoring and consumption analysis.

- Configuration of control scenarios, temperature setpoints, and energy optimization strategies directly within the Loxone architecture.

- The entire installation was completed in 20 days, while the building remained operational, with precise phasing of interventions to guarantee business continuity.

This installation now provides the site with a clear and structured view of its energy consumption, while improving the management of thermal and energy-intensive equipment. Controlling the air heaters via two-way valves, combined with heat metering, allows for better control of usage and precise regulation of heating by unit. The solution also provides a scalable foundation for further energy optimization and long-term performance monitoring, while maintaining occupant comfort and the site's operational continuity.

Products

  • Miniserver · 100335
  • Modbus Extension · 100124
  • Relay Extension · 100038
  • DI Extension · 100283
  • AO Extension · 100382
  • M-Bus Extension · 100569

To overview